3 Packaging and Handling
The switchboard lineup is shipped in single sections or shipping splits. Separation of splits are deemed by the project
engineer and their communication with the customer. Unless otherwise requested, the single sections or splits will be
wrapped and shipped on a pallet to which they are bolted. The standard size of the pallet is the width of the section or split by
the depth of the section plus twelve inches (approximately six inches in the front and rear of the switchboard when centered
on the pallet). Each section is unique to the job, thus the section weights vary. For actual weights and dimensions, consult
equipment shipping documentation.
3.1 Receiving
•Ensure all sections and splits are present when switchboard arrives on site. Notify your Vertiv representative if
any anomalies are found.
•A thorough inspection should be performed to make sure no damages occurred during shipment. If damages did
occur, a qualified technician needs to investigate the gear for proper diagnosis.
•If the damage is from improper handling, contact the carrier and your Vertiv representative.
•All sections are inspected and marked before they leave the facility. It will be clearly marked with what side is the
front, as well as the section or split number.
•A plastic cover should be used to protect the equipment from dust, dirt, moisture, and damage until it is ready for
installation. The switchboard should remain attached to the pallet until it has been moved into its final installation
position.
•All packaging material should be saved until the gear is ready to be installed, especially if there is a delay in the
installation, so that it can be repacked and stored safely. See Storage on page20 if a delay occurs.
3.2 Handling
Most switchboard sections are top and front heavy and should be handled with caution. Before moving or lifting any section,
verify that the equipment that is going to be used to handle the switchboard is within the safe limits of its capacity.
3.2.1 Unloading from Truck
A forklift is the best method for unloading the switchboard.
IMPORTANT! Only trained personnel should drive the forklift and move the switchboard. Make sure the ground is
solid and all operation and safety recommendations are followed while operating the forklift.
NOTE: Be aware of any floors and conditions that could affect stopping and turning. Pay attention to labeling on the
packaging material. Make sure that the forklift being used is rated to work in safe limits for the weight of the
switchboard split being lifted.
1. Lift the switchboard sections from the front or back side.
2. The forks must run all the way through the entire shipping length and extend past the outermost part of the
wooden pallet.
3. A safety strap, belt or leash approved for the purpose of securing the section should be used. Make sure the
position of the strap is adequate in providing stability to the equipment, in a location that will not damage any
components.
4. Slowly lift the equipment to the minimum required height from the floor for safe relocation.
3 Packaging and Handling Proprietary and Confidential ©2024 Vertiv Group Corp. 13