GENERAL
The BKON™Craft Brewer is designed for high volume
use, for the creation of “quick serve / on demand”
drinks prepared by a Barista (operator). The machine
ships from the factory in two parts: tower and supply
center. The tower is where the product is brewed and
dispensed. A brew handle is used to hold product during
a brew cycle.
Cold water should be supplied to the unit. During
a cycle, 8 to 20 oz. of water passes through three
thermoblock heaters (requiring a 208 - 230 volt, 30
amp circuit). Lower temperatures are achieved by
use of a mixing cold water with hot. The BKON Craft
Brewer utilizes a vacuum pump to reduce air pressure
inside the brew cylinder during the brew cycle. A water
supply connection is located on the front of the supply
center and should be connected per national and local
municipality codes and regulations.
PRE-INSTALLATION
1. Water Pressure is very important.
Ensure sure incoming water pressure is between
30 and 90 psi. BKON brewer should not be
installed if pressure is outside this range.
2. Remove BKON™Craft Brewer from shipping
carton
This unit will arrive in a skid-mounted carton.
Examine shipping cartons and unit for damage
prior to unpacking. Immediately photograph any
damage for possible claim purposes.
CAUTION
The shipping container may have staples and will have
banding under tension, which can cause injuries. Wear
gloves and eye protection to reduce the risk of injury
when removing the banding from the carton.
-Cut the plastic banding using heavy scissors or tin
snips.
-Use caution to avoid contact with banding, when
cut.
-Lift cardboard carton straight up and off unit.
3. Leave Unit on Skid Until Ready to Place on
Counter
CAUTION
The unit and shipping skid combined weigh
approximately 185 lbs (84 kg). Do not attempt to remove
it from the shipping skid without assistance or the use of
proper lifting equipment.
PRE-INSTALLATION / DELIVERY
4. Remove Packing & Loose Components
The BKON Craft Brewer unit consists of a brew
tower and a supply center that are all secured
so they will not open or shift during shipping.
The shipment also includes loose components
which include brew handles and brew baskets,
communications cable, lines and hardware.
Remove any other boxes from the shipping skid,
and then remove any tape and foam blocking
securing the components in place.
-Peel the protective white plastic film from all
stainless steel surfaces.
5. Electrical Preparation
Before you set this unit in place, locate the
appropriate 208-volt power outlet. A power
cord with plug is provided attached to the water
vacuum supply center. This power cord is
hardwired into the water vacuum supply center.
6. Plumbing Preparation
Before installing, verify plumbing (water, drain)
and electrical accommodations are provided
at the installation location. Make sure the drain
piping is clear of any leaks or obstructions.
NOTICE
The tower must be mounted on a counter that meets
NSF splash zone requirements.
7. Tools required
2 adjustable wrenches, 1 Phillips screwdriver, 1
tube of clear silicone, 1 3/8” water supply line,
1 3/4” hose connection for drain, 1 5’ drain hose,
1 hose clamp, wire ties.