AMGO PRO-18A Manual

FOUR POST LIFT
Model: PRO-18(A)
PRO-18
PRO-18A
Original

CONTENTS
Product Features and Specifications ..................................................... 1
Installation Requirement .................................................................... 2
Steps of Installation ........................................................................ 4
Exploded View ................................................................................. 23
Test Run ......................................................................................... 32
Operation Instruction ....................................................................... 33
Maintenance ................................................................................... 33
Trouble Shooting ............................................................................. 34
List Disposal......................................................................................34

1
I. PRODUCT FEATURES AND SPECIFICATIONS
MODEL PRO-18(A) FEATURES
· Manual control system.
· Mechanical self-lock and air-drive safety release.
·Hydraulic power system, cable-drive.
· Strengthen and Non-skid diamond platforms.
· Multiple turn plate pockets fit with different wheel base.
· Adjustable platform and adjustable safety lock ladders.
· Optional Jack:With hand pump/Air-operated hydraulic pump/Controlled by power
unit.
. Optional Turn plate (Only for PRO-18A)
MODEL SPECIFICATIONS
Model
Lifting
Capacity
Lifting
Height
Lifting
Time
Overall
Length
(Inc.
Ramps)
Overall
Width
Width
Between
Columns
Motor
PRO-18
18000LBS
73-1/2”
81S
293-1/4”
137-1/8”
122-3/8”
2.0HP
PRO-18A
18000LBS
75-3/8”
81S
292-3/4”
137-1/8”
122-3/8”
2.0HP
PRO-18
Fig.1
PRO-18A
Fig.2

2
II. INSTALLATION REQUIREMEN
A. TOOLS REQUIRED
Rotary Hammer Drill (Φ3/4)Carpenter’s Chalk
Hammer Screw Sets
Level Bar Tape Measure (295”)
English Spanner (12") Pliers
Wrench Set
Lock Wrench
(10#, 12#, 13#, 14#, 17#, 19#, 24#, 30#)
Ratchet Spanner With Socket (28#)
Socket Head Wrench
(3#, 5#, 6#)
Fig. 3

- 3 -
B. Equipment storage and installation requirements.
The equipment should be stored or installed in a shady, normal
temperature, ventilated and dry place.
C. SPECIFICATIONS OF CONCRETE (See Fig. 4)
Specifications of concrete must be adhered to the specification as following.
Failure to do so may result in lift and/or vehicle falling.
1. Concrete must be thickness 7-7/8” mm minimum and without reinforcing steel
bars,and must be dried completely before the installation.
2. Concrete must be in good condition and must be of test strength 3,000 psi
minimum.
3. Floors must be level and no cracks.
D. AIR SUPPLY
Air pressure requirement: 0.5Mpa~0.8Mpa, Air line size Φ8 *Φ6and Φ6 *Φ4.
E. POWER SUPPLY
The electrical source must be 2.0HP minimum. The source cable size must be 2.5mm²
and in good condition of contacting with floor.
Fig. 4
≥7-7/8”
Concrete Intensity must be 3000PSI minimum

- 4 -
×
√
III. STEPS OF INSTALLATION
A. Location of installation
Check and insure the installation location (concrete, layout, space size etc.) is
suitable for lift installation.
B. Check the parts before assembly
1, The equipment should be unload and transfer by forklift. (See Fig.5)
2. Received lift and hydraulic power unit (See Fig. 6).
3. Open the outer packing carefully, check all the parts according to the parts list (See
Fig. 7).
Shipment Parts List
Fig. 6
Fig. 5
Power side Platform
Drive-in Ramp
Offside Platform
Cross Beam
Column
Fig. 7
Parts box

- 5 -
4. Take off the Drive-in Ramps and Columns (See Fig. 8).
5. Loose the screws of the upper package stand, take off the offside platform, take out
the parts inside the power side platform, than remove the package stand.
6. Move aside the parts and check the parts according to the shipment parts list (See
Fig. 9,Fig.10).
6.1 Model PRO-18
Fig. 8
Fig.9

- 6 -
6.2 Model PRO-18A
7. Open the carton of parts and check the parts according to the parts box list
(See Fig. 11).
Fig. 11
Fig.10

- 7 -
8. Check the parts of the parts bag according to the parts bag list (See Fig. 12).
Fig.12
Parts bag 2
Parts bag 1 for PRO-18A
Parts bag 1 for PRO-18

- 8 -
C. Use a carpenter’s chalk line to establish installation layout, Make sure the size is
right and base is flat.(see Fig.13)
Note: Reserve space before and behind the installation site.
Model
A
B
C
PRO-18
PRO-18A
252-1/4”
137-1/8”
287-1/8”
Fig. 13
Use a carpenter’s chalk line to establish
installation layout
Car in Direction

- 9 -
D. Install cross beams (See Fig. 14, Fig. 15).
Fig. 14
Fig. 15
2
Hole towards inside
1
3
3

- 10 -
E. Fix the anchor bolts
1. Prepare the anchor bolts (See Fig. 16).
2. Using the prescribed rotary hammer drill, and drill all the anchor holes and install the
anchor bolts, do not tighten the anchor bolts first (See Fig. 17).
Note: Minimum embedment of anchors is 110mm
F. Install the safety ladders
1. Take off the pulley safety cover and unscrew the four upper nuts of the Safety
Ladders, and then adjust the four lower nuts to be at the same position. Withdraw
the Slack-cable safety lock of the Cross-beam to insert the Safety Ladder in, raise
the Safety Ladder, and screw the upper nuts (See Fig. 18).
Fig. 18
6
Nut
Spring washer
Washer
Fig. 16
Safety Ladder is
inserted between
Limit Pins
Limit Pin
Limit Pin
Safety Ladder
Safety Ladder is
inserted between Limit Pins
5
Drilling
Clearing
Expand
5
Fig. 17
110mm

- 11 -
2. Install safety ladders (See Fig. 19).
G. Put the Cross Beams at the same height (See Fig. 20).
Fig. 19
Safety ladder pass through
the hole of the top plate,
then tighten the two nuts
7
This height should
be the same for
four safety ladders
6
Fig. 20
Lifting Both Cross Beams to the
same height, it is recommended
to about 1 meter height
The four primary safety
locks are adjusted to be
locked to the safety
ladders at the same time
Lifting Both Cross Beams to the same
height

- 12 -
H. Install power side platform.
1. Put the power side platform upon the cross beams by fork lift or manual, offset the
cross beams to the outside till the pulleys of both platforms can set up into the cross
beam (See Fig.21), Install the power side platform and screw up the bolts.
8
15
16
17
Pulley installation
Fig.21
Offset the cross beam
lean outward when
putting the power-side
platform on the cross
beams
Install the power-side platform
and screw up the bolts M20*40
Offset the cross beam
lean outward when
putting the power-side
platform on the cross
beams

- 13 -
I. Assembly offside platform and slider block, check the vertical of columns with
level bar, adjusting with the shims if not, and then tighten the anchor bolts (See Fig.
22).
Using the ratchet spanner with
socket to tighten the bolts
Fig. 22
46
18
8
Install the slider block
3-15
3-16
3-14
Note: Torque of Anchors is
150N.m.

- 14 -
J. Install cables
1. Pass through the cables from the platform to the columns according to the number of
the cables (See Fig. 23).
No.
Cable
○
1
○
2
○
3
○
4
Length for PRO-18 (A)
(inc. connecting fitting)
198-5/8”
515-3/4”
271-1/2”
442-1/8”
Fig. 23
A
D
B
C
60
61
62
63
Fig. 23
B
B
B
D
B
C
B
A

- 15 -
2. The cable pass through the cross beam to top plate of columns and be screwed with
cable nuts (See Fig. 24).
Cable pass through
between the big pulley
and tension pulley
83
Cable pass through top
plate and be screwed
with cable nuts.
Fig. 24
Install limit pin
Cable
48
Pulley
47
Limit
pin
After install limit pin

- 16 -
3. Illustration for platform cables (See Fig. 25).
Limit slider
Fig. 25
Hex Bolt M10*150
cable ④
cable ②
19
cable ①
cable ②
cable ④
cable ②
cable ③
cable ④
cable ④
cable ②
cable ②
cable ①
cable ④
cable ③
Limit block

- 17 -
K. Install Oil-water separator, Manual control air valve and Power unit
(See Fig. 26).
Item
Part#
Description
QTY
20
10420145
Oil water separator AFR-2000
1
21
10420146
Straight Fitting for air line
1
22
10209009
Cup Head Bolt
8
23
10420076
Fitting
1
24
10420159
Straight Fitting
1
25
11420160
Fixing plate of Manual Control Valve
1
26
10420161
Self locking nut
2
27
10420162
Manual Control Air Valve
1
28
10420163
Straight Fitting for Air Line
1
29
10420148
Washer
4
30
10420164
Cup Head Bolt
2
31
81513003/81513004
Manual power unit
1
32
10209005
Self locking nut
14
33
10209004
Rubber Ring
4
34
10209003
Hex Bolt
4
Fig. 26
24
25
26
22
28
29
30
31
27
1
20
21
22
23
32
33
34
Air flow of air solenoid valve
Air
flow
The ”P” side on air
solenoid valve is
for Air inlet
Air outlet
Air inlet
Air flow of oil water
separator

- 18 -
L. Install Hydraulic System (See Fig. 27).
Note: Oil hoses connected to oil cylinder must be passed above the cable, cylinder
inlet port must swing upward to avoid the oil hose and oil return pipe scratched
by cable.
Oil hose and air line
pass through the
retainer
76
70
69
Protective ring
cylinder fitting swing upward
Cylinder oil return hose
installation
76
Installation diagram for oil
return hose and oil inlet
hose
68
66
Fig.27
Other manuals for PRO-18A
1
This manual suits for next models
1
Table of contents
Other AMGO Lifting System manuals