AV 8 Installation Manual Issued October 2000 Page 2
INTRODUCTIONINTRODUCTION
This manual provides the detailed procedures for installing the OMNI AV-8
Key Telephone System. Read this entire section before proceeding with the
actual installation.
Prior to installation carefully inspect all packages for evidence of damage and
compare the equipment received against equipment ordered to ensure ALL
components have been received.
SITE REQUIREMENTSITE REQUIREMENT
lThe Key System Unit (KSU) should be installed in a clean, dry and secure
location accessible only by authorized personnel. The location must have
adequate ventilation and the temperature range within 0 ~ 45o C with a 10 ~ 90%
non-condensing relative humidity.
lThe installation site should have sufficient room to mount the KSU on a wall,
along with the necessary connecting blocks and ancillary equipment. The
installation site should not be in areas subject to static electricity (eg. dry copiers,
electric welders), or vibration (eg. heavy machinery).
lIt is the customer’s responsibility to provide a dedicated 240VAC/50Hz 10 Amp
mains power outlet. Line Isolation Units (LIUs) must be provided if an external
music source or optional external paging equipment is installed.