S&C Instruction Sheet 1023-510 7
Installing the Capacitor Control
Follow these steps to install the capacitor control:
STEP 1. Read the following warnings before installing or operating this equipment:
WARNING
This control is connected to capacitors operating at primary voltage levels. High
voltage may be present in the wiring to the control or the control itself during cer-
tain malfunctions of the capacitor bank wiring or grounding system or because of a
malfunction of the capacitor bank itself. For this reason, access to the control should be
treated with the same safety precautions that would be applied when accessing other
high-voltage lines and equipment. Follow all locally approved safety procedures when
working on or around this control.
When open-circuited, current transformers can produce high voltages that can result
in injury or death. Proper shorting hardware and operating procedures are required for
safe operation. The current transformer must be shorted before installing or removing
the control. This control does NOT provide for shorting of the current transformer.
WARNING
Do not energize the 110-240 Vac power source entering the control enclosure until all
wiring is complete.
Do not plug the sensor cable into the control until called for in the instructions.
Do not enable communications by connecting radios, fiber-optic cables, or dedicated
phone lines until this is called for in the instructions.
Before attempting to access an existing installation, check carefully for visible or
audible signs of electrical or physical malfunction—do this before touching or operat-
ing the control or any other part of the installation. These warning signs include such
things as smoke, fire, open fuses, crackling noises, loud buzzing, etc. If a malfunction is
suspected, treat all components of the installation, including the control and associated
mounting hardware, as if they were elevated to primary (HIGH) voltage.
You must follow the sequence of installation steps outlined in this instruction sheet to
insure a safe and successful control installation.
WARNING
These instructions do NOT replace the need for utility operation standards. Any conflict
between the information in this document and utility practices should be reviewed by
appropriate utility personnel and a decision made as to the correct procedures to follow.
The S&C IntelliCap Plus Automatic Capacitor Control is connected to switchgear
operating at primary voltage levels. High voltage may be present in the wiring to the
switch control or the switch control itself during certain failures of the switchgear wiring
or grounding system, or because of a failure of the switch itself. For this reason, access
to the switch control should be treated with the same safety precautions that would
be applied when accessing other high-voltage lines and equipment. Follow all locally
approved safety procedures when working on or around this switch control.
Before attempting to access an existing switch installation, check carefully for vis-
ible or audible signs of electrical or physical malfunction (do this before touching or
operating the switch control or any other part of the installation). These warning signs
include such things as smoke, fire, open fuses, crackling noises, loud buzzing, etc. If a
malfunction is suspected, treat all components of the installation, including the switch
control and associated mounting hardware, as if they were elevated to primary (high)
voltage.
STEP 2. Remove the load fuse.
Remove the 10-A fuse near the lower right corner of the faceplate. See Figure 1
on page 8.
On-Site Installation