Stratus SAE-C10P Guide

Model No. SAE-C10P
Direct drive 2 post Lift
Single Point Manual Release
Lifting Capacity 10,000 lbs
Installation & Operation &
Maintenance Instructions
Important Note
1. This equipment can not be installed, operated or repaired without reading instructions.
2. Electricity must be hooked up by certified electrician.
3. Do not use this equipment beyond its rated capacity.

STRATUS Clear Floor 2 post Lift Installation & Operation & Maintenance Instructions
2
TABLE OF CONTENTS
1. Packing, transport and storage .......................................................................................................................................5
1.1 Packing..............................................................................................................................................................................5
1.2 Transport...........................................................................................................................................................................5
1.3 Storage..............................................................................................................................................................................5
2. Technical specifications ....................................................................................................................................................6
3. Safety......................................................................................................................................................................................9
3.1 Important notices .............................................................................................................................................................9
3.2 Qualified personnel .........................................................................................................................................................9
3.3 Danger notices.................................................................................................................................................................9
3.4 Training..............................................................................................................................................................................9
3.5 Warning signs.................................................................................................................................................................10
4. Installation...........................................................................................................................................................................11
4.1 Tool required...................................................................................................................................................................11
4.2 Checking for room suitability........................................................................................................................................12
4.3 Lighting.......................................................................................................................................................................12
4.4 Floor requirement .....................................................................................................................................................12
4.5 Site layout..................................................................................................................................................................12
4.6 Assemble columns.........................................................................................................................................................13
4.7 Installation overhead top beam ...................................................................................................................................14
4.8 Position columns ......................................................................................................................................................16
4.9 Install overhead top beam ............................................................................................................................................17
4.10 Install limit switch.........................................................................................................................................................18
4.11 Adjust carriage..............................................................................................................................................................20
4.12 Install cables (2 Cables in total ) ...............................................................................................................................20
4.13 Routing the safety release cable...............................................................................................................................21
4.14 Installation of power unit.............................................................................................................................................22
4.15 Connection of hydraulic hoses ..................................................................................................................................22
4.16 Make the electrical connection ..................................................................................................................................23
4.17 Oil filling and bleeding.................................................................................................................................................23
4.18 Installation of lifting arms and adjustment of arm locks.........................................................................................24
4.19 Check before start-up .................................................................................................................................................26
4.19.1 General checks...................................................................................................................................................26
4.19.2 Mechanical safeties for proper installation.................................................................................................26
4.19.3 Equalizer cable for proper installation .........................................................................................................26
4.19.4 Hydraulic system for proper operation........................................................................................................26
4.20 Check with load ...........................................................................................................................................................26
5. Operation and use.............................................................................................................................................................27
5.1 Controls...........................................................................................................................................................................27
5.2 Vehicle positioning....................................................................................................................................................27
5.3 Lifting..........................................................................................................................................................................27
5.4 Standing.....................................................................................................................................................................28
5.5 Lowering ....................................................................................................................................................................28
6. Maintenance........................................................................................................................................................................29
6.1 Ordinary maintenance...................................................................................................................................................29
6.2 Periodic maintenance....................................................................................................................................................29
7. Troubleshooting.................................................................................................................................................................30
8. Parts list ...............................................................................................................................................................................31
8.1 Explosive view and parts list ........................................................................................................................................31
8.2 Hydraulic system and parts list....................................................................................................................................33
8.3 Steel cable assembly and parts list.............................................................................................................................34
8.4 Safety lock system and parts list.................................................................................................................................35
8.5 Cross beam assembly and parts list...........................................................................................................................37
8.6 Lifting carriage and parts list ........................................................................................................................................39
8.7 Arm assembly and parts list .........................................................................................................................................40

STRATUS Clear Floor 2 post Lift Installation & Operation & Maintenance Instructions
3
9. Special notes ......................................................................................................................................................................42
9.1 Environmental damage.................................................................................................................................................42
9.2 Dismantling.....................................................................................................................................................................42
9.3 Disposal ..........................................................................................................................................................................42
9.4 Noise declaration...........................................................................................................................................................43

STRATUS Clear Floor 2 post Lift Installation & Operation & Maintenance Instructions
4
Foreword
Notes on the operating instructions
The present ORIGINAL OPERATING INSTRUCTIONS are designed to provide sufficient instruction for the
safe operation of the product. The information is provided clearly and concisely. The chapters are arranged
by letter and the pages are numbered continuously.
Our products are subject to ongoing development. Our company reserves the right to alter the design,
equipment and technical features of the system. No guarantee of particular features of the product should
therefore be assumed from the present operating instructions.
Safety notices and text mark-ups
Safety instructions and important explanations are indicated by the following graphics:
Indicates an extremely hazardous situation. Failure to comply with this instruction will result in
severe irreparable injury and even death.
Indicates an extremely hazardous situation. Failure to comply with this instruction may result in
severe irreparable injury and even death.
Indicates a hazardous situation. Failure to comply with this instruction may result in
slight to medium injury.
Indicates a material hazard. Failure to comply with this instruction may result in material damage.

STRATUS Clear Floor 2 post Lift Installation & Operation & Maintenance Instructions
5
1. Packing, transport and storage
All packing, lifting, handling, transport and unpacking operations are to be performed exclusively by expert
personnel with knowledge of the lift and the contents of this manual.
1.1 Packing
The packing of the lift is delivered in following components:
•1 base unit packed in a steel frame, wrapped up in non-scratch material, including all the accessories.
•1 power unit packed in a carton box.
1.2 Transport
See Fig 1, packing can be lifted or moved by lift trucks, cranes or bridge cranes. In case of slinging, a second
person must always take care of the load, in order to avoid dangerous oscillations.
During loading and unloading operation, goods must be handled by vehicles or ships.
At the arrival of the goods, verify that all items specified in the delivery notes are included. In case of missing
parts, possible defects or damage due to transport operations.
If finding missing parts, possible defects or damage due to transport, one should examine damaged cartons
according to <<Packing List.>> to verify the condition of damaged goods and missing parts, also the person in
charge or the carrier must be immediately informed.
The machine is heavy goods! Don’t take manpower load and unload and transporting way into consideration, the
safety of working is important.
Furthermore, during loading and unloading operation goods must be handled as shown in the picture. (Fig 1)
Fig 1
1.3 Storage
The machine equipment should be stocked in the warehouse, if stocked outside should do the disposal well of
waterproof.
Use box truck in the process of transport, use container storage when shipping.
The control box should be placed perpendicularly during the transport; and prevent other goods from extrusion.
The temperature for machine storage: -10ºC-- 40ºC

STRATUS Clear Floor 2 post Lift Installation & Operation & Maintenance Instructions
6
2. Technical specifications
Model
SAE-C10P
Symmetric Installation
Asymmetric Installation
Lifting capacity
10,000lbs(4,500KG)
10,000lbs(4,500KG)
Lifting height
74 13/16"(1900mm)
74 13/16"(1900mm)
Min. height
3 15/16"(100mm)
3 15/16"(100mm)
Column inside
118 1/8"(3000mm)
115 3/8"(2930mm)
Drive through
107 1/16”(2720mm)
103 15/16"(2640mm)
Lifting time
About 50 sec.
About 50 sec.
Lowering Time
About 40 sec.
About 40 sec.
Column thickness of steel
3/16"(5.0mm)
3/16"(5.0mm)
Carriage thickness of steel
3/16"(5.0mm)
3/16"(5.0mm)
Arms thickness of steel
1/4"(6.0mm)
1/4"(6.0mm)
Voltage
220V
220V
Power
2.2Kw
2.2Kw
Frequency
60Hz
60Hz
Phase
1Ph
1Ph
Breaker
30A
30A
Hydraulic oil
AW46
/
AW32
AW46/AW32
Shipping Size
2920*620*630mm/
2920*620*630mm/
115"×24"×25"
115"×24"×25"
Equipment weight
1446lbs(656KG)
1446lbs(656KG)

STRATUS Clear Floor 2 post Lift Installation & Operation & Maintenance Instructions
7
Symmetric Installation
Fig. 2

STRATUS Clear Floor 2 post Lift Installation & Operation & Maintenance Instructions
8
Asymmetric Installation
Fig. 3

STRATUS Clear Floor 2 post Lift Installation & Operation & Maintenance Instructions
9
3. Safety
3.1 Important notices
This 2-posts lift is specially designed for lifting motor vehicles that weighs within its outmost lifting capacity. Users
are not allowed to use it for any other purposes. Otherwise, we, as well as our sales agency, will not bear any
responsibility for accidents or damages of the lift. Make sure to pay careful attention to the label of the lifting
capacity attached on the lift and never try to lift cars with its weight beyond.
Read this manual carefully before operating the machine so as to avoid economic loss or personnel casualty
incurred by wrong operation. Without professional advice, users are not permitted to make any modification to the
control unit or whatever mechanical unit.
3.2 Qualified personnel
➢Only these qualified staff, who have been properly trained, can operate the lift.
➢Electrical connection must be done by a competent electrician.
➢People who are not concerned are not allowed in the lifting area.
3.3 Danger notices
➢Do not install the lift on any asphalt surface.
➢Read and understand all safety warnings before operating the lift.
➢The lift, if is not specially designed upon customer’s request, is not fit for outdoor use.
➢Keep hands and feet away from any moving parts. Keep feet clear of the lift when lowering.
➢Only these qualified people, who have been properly trained, can operate the lift.
➢Do not wear unfit clothes such as large clothes with flounces, tires, etc, which could be caught by moving
parts of the lift.
➢To prevent evitable incidents, surrounding areas of the lift must be tidy and with nothing unconcerned.
➢The lift is simply designed to lift the entire body of vehicles, with its maximum weight within the lifting capacity.
➢Always ensure the safety latches are engaged before any attempt to work near or under the vehicle.
➢Make sure to place the lifting pads to the positions as suggested by vehicle makers and when gradually lift the
vehicle to the desired height, operators should be certain that the vehicle will not slant, roll-over or slide in
lifting process.
➢Check at any time the parts the lift to ensure the agility of moving parts and the performance of
synchronization. Ensure regular maintenance and if anything abnormal occurs, stop using the lift immediately
and contact our dealers for help.
➢Lower the lift to its lowest position and do remember to cut off the power source when service finishes.
➢Do not modify any parts of the lift without manufacturer’s advice.
➢If the lift is going to left used for a long time, users are required to:
a. Disconnect the power source;
b. Empty the oil tank;
c. Lubricate the moving parts with hydraulic oil.
3.4 Training
Only these qualified people, who have been properly trained, can operate the lift. We are quite willing to provide
professional training for the users when necessary.
Attention: For environment protection, please dispose the disused oil in a proper way.

STRATUS Clear Floor 2 post Lift Installation & Operation & Maintenance Instructions
10
3.5 Warning signs
All safety warning signs attached on the machine are for the purpose of drawing the user’s attention to safety
operation. The labels must be kept clean and need to be replaced when they are worn-out or have dropped. Read
the explanations of the labels carefully and try to memorize them.

STRATUS Clear Floor 2 post Lift Installation & Operation & Maintenance Instructions
11
4. Installation
Only skilled technicians, appointed by the manufacturer, or by authorized dealers, must be allowed to
carry out installation. Serious damage to people and to the lift can be caused if installations are made by
unskilled personnel.
Always refer to the exploded views attached during installation.
4.1 Tool required
Rotary Hammer Drill D.20
Carpenter’s Chalk
Hammer
Screw Sets
Level Bar
Tape Measure (7.5m)
English Spanner (12")
Pliers
Ratchet Spanner With Socket (28#)
Socket Head Wrench (3#, 5#, 8#)
Wrench set
(10#, 13#, 14#, 15#, 17#, 19#, 24#, 27#, 30#)
Lock Wrench

STRATUS Clear Floor 2 post Lift Installation & Operation & Maintenance Instructions
12
4.2 Checking for room suitability
The lift has been designed to be used in covered and sheltered places free of overhead obstructions.
The place of installation must not be next to washing areas, painting workbenches, solvent or varnish deposits.
The installation near to rooms, where a dangerous situation of explosion can occur, is strictly forbidden. The
relevant standards of the local Health and Safety at Work regulations, for instance, with respect to minimum
distance to wall or other equipment, escapes and the like, must be observed.
4.3Lighting
Lighting must be carried out according to the effective regulations of the place of installation. All areas next to the
lift must be well and uniformly lit.
4.4Floor requirement
The lift MUST be installed on 3000 PSI concrete with the minimum thickness 6” and an extension of at least 4’
from anchoring points. New concrete must be adequately cured by at least 20 days minimum.
Specifications of concrete must be adhered to. Failure to do so could cause lift failure resulting in
personal injury or death.
A level floor is suggested for proper installation. Small differences in floor slope may be compensated for
by proper shimming. Any major slope change will affect the level lifting performance. If a floor is of
questionable slope considering to pour the new concrete slab.
4.5Site layout
• Now locate the lift according to the floor plan the figure 4 & 5, use a carpenters chalk line to layout a grid for the
column locations.
• After the column locations are properly marked, use a chalk or crayon to make an outline of the columns on the
floor at each location using the column base plates as a template.
• Double check all dimensions and make sure that the bases of each column are square and aligned with the
chalk line.
Fig. 4 – Symmetric Installation Floor Plan

STRATUS Clear Floor 2 post Lift Installation & Operation & Maintenance Instructions
13
Fig. 5 Asymmetric Installation Floor Plan
4.6 Assemble columns
Assemble main column & extension column, and then stand up the 2 columns (the column with the power unit
base plate is the main column and the other one is the vice column) (Fig 6)
Note: Don’t drill anchor bolts holes or install anchor bolts now.
Fig. 6

STRATUS Clear Floor 2 post Lift Installation & Operation & Maintenance Instructions
14
4.7 Installation overhead top beam
1. Assemble overhead top beam (See Fig.7)
NOTE: The bolts run from inside of the column and then fasten the nuts from outside of the column.
Fig. 7
2. Install the overhead beam cable pulley.
Warning: Symmetrical installation and asymmetrical installation of the cable pulley positions are not universal. In-
correct installation of the pulley positions may cause damage to the cable or the lift.
A. For symmetrical installation, use the long shaft and the long shaft sleeve to fix the cable pulley (pre-installed)
(See Fig.8).
B. For asymmetric installation, use 4 short shafts and 2 short shaft sleeves in the accessory box to fix the cable
pulley (See Fig.9)
Fig. 8 Symmetric Installation

STRATUS Clear Floor 2 post Lift Installation & Operation & Maintenance Instructions
15
Fig. 9 Asymmetric Installation
C. Mounting position of cable pulley (Fig.10)
Note: During the installation, the positions of the cable pulley at both ends of the overhead beam should be
installed correspondingly. There may be a gap between the cable pulley and the shaft sleeve, this is for the cable
can be automatically aligned, normal abrasion. Do not add shim to fix the position of pulley, it may cause abnormal
wear of the lift.
Fig. 10 Cable Pulley Position

STRATUS Clear Floor 2 post Lift Installation & Operation & Maintenance Instructions
16
4.8Position columns
Check if the columns are vertical to the ground with level, insert thin shims (come with package) to adjust when
necessary
Fig. 11 Symmetric installation
Fig. 12 Asymmetric installation

STRATUS Clear Floor 2 post Lift Installation & Operation & Maintenance Instructions
17
4.9 Install overhead top beam
1.When symmetrical installation method is adopted, cable pulley (refer to Fig. 10) should be installed according in
a symmetrical manner and fix the 6 screws underneath the overhead beam (Fig. 13)
2.When asymmetrical installation is adopted, cable pulley (refer to Fig. 10) should be installed according in
asymmetrical manner and fix the 5 screws underneath the overhead beam (Fig 14).
Fig. 13 Symmetric Install overhead top beam
Fig. 14 Asymmetric Install overhead top beam

STRATUS Clear Floor 2 post Lift Installation & Operation & Maintenance Instructions
18
4.10 Install limit switch
1. View of the two limiter switches (Fig.15):
Fig. 15
2. Install the limiter switch A on the cross beam (Fig. 16):
Fig. 16
Limiter switch A is
installed on the cross
beam
Limiter switch B is
installed on the main
column
Connect to motor

STRATUS Clear Floor 2 post Lift Installation & Operation & Maintenance Instructions
19
3. Install the limiter switch B inside of the main column (Fig. 17):
Fig. 17
4. Connect the limiter switch connector to the motor (Fig. 18):
Fig. 18

STRATUS Clear Floor 2 post Lift Installation & Operation & Maintenance Instructions
20
4.11 Adjust carriage
Raise the carriage to the 1st locking position located at the bottom of the column (Fig. 19).
Note: You can hear “click” once locked (the 1st locking position is about 11.8” from the ground).
Fig. 19
4.12 Install cables (2 Cables in total )
Note: Please pay attention to the change of the hanging point of the cable during symmetrical installation (Fig.20)
and asymmetrical installation (Fig. 21) during the installation.
Fig. 20 Symmetric Installation Cable Routing
Table of contents
Other Stratus Lifting System manuals

Stratus
Stratus SAE-P166M Guide

Stratus
Stratus SAE-C12X Guide

Stratus
Stratus SAE-C14X Guide

Stratus
Stratus SAE-C9P Guide

Stratus
Stratus SAE-F10P Guide

Stratus
Stratus SAE-UT8000 Guide

Stratus
Stratus SAE-P48 Guide

Stratus
Stratus SAE-C10C Guide

Stratus
Stratus MS9000XT User manual

Stratus
Stratus SAE-S66M User manual